Huitt-Zollars provided sewer system master planning for this 445-acre planned industrial park. Design and construction services associated with 8,000 linear feet of on-site sewer system improvements were provided for Phase 1 (125 acres) of the project. In addition, Huitt-Zollars managed and designed a 20-MGD sewage pump station and three 20-inch diameter HDPE, and 12,500 linear feet of sanitary sewer force mains that convey sewage from the pump station to an existing 48-inch gravity sewer. Force main design challenges included crossing two active railroad lines and two arterial roadways. In addition, Huitt-Zollars has most recently provided Phase 2 sewer system design for an additional 90 acres of development.
Wastewater Master Plan
Longview
Client
City of Longview